I've also posted a draft update I had been working on. It's a little out of date.
Here's the latest progress update:
1. All windows and doors have been installed except our garage door which is going in this week.
2. We have heat in all the renovated spaces. Our heated floors are in as is our gas fireplace in the back room.
3. Tiling is almost complete. They have the rear bathroom and half the back took to finish.
4. Electrical and plumbing rough-in and boiler/heating mods have been completed.
5. Roofing has been completed except for a small alteration to the flat roof, which should be happenning this week.
6. The lower kitchen cabinets have been installed so that we will have the granite countertops for Christmas.
7. Stucco is being done this week under heated tarps.
I will update again later this week but with any luck, we'll have a kitchen by Christmas!